United Kingdom-Birmingham: Construction management services
2018/S 154-354264
Contract notice – utilities
Services
Directive 2014/25/EU
Section I: Contracting entity
Diamond House, Procurement
Birmingham
B26 3QJ
United Kingdom
Contact person: Procurement
Telephone: +44 1217677389
E-mail: MjIwXF5bT2FeUVlRWmAsTlVeWVVaU1RNWU1VXlxbXmAaT1saYVc=
NUTS code: UKG31
Internet address(es):
Main address: www.birminghamairport.co.uk
Section II: Object
Terminal Expansion Works at Birmingham Airport (TE18)
Birmingham Airport is seeking to appoint a Construction Manager to identify the optimum phased packages of work necessary to deliver the construction of the Terminal Extension 3 (TE18) Project, to lead in the procurement of these work packages on behalf of the Airport and to manage the delivery of the work packages so as to ensure that the Project is delivered to time, cost and quality. The scope of the TE18 project is, in summary the construction of a new three storey extension to the existing terminal building, circa 10 000 m2.
The works comprise:
— Demolition of existing slabs and structures as required for the works
— All groundworks and provision of new foundations as required by the design
— Installation of new structural frame, cladding and roofing works.
— Installation of Mechanical, electrical and public health systems. Integration of these systems with the Airport’s wider MEP systems where specified.
— Internal fit out of client spaces.
— New drainage runs
Birmingham Airport
Birmingham Airport is seeking to appoint a Construction Manager to identify the optimum phased packages of work necessary to deliver the construction of the Terminal Extension 3 (TE18) Project, to lead in the procurement of these work packages on behalf of the Airport and to manage the delivery of the work packages so as to ensure that the Project is delivered to time, cost and quality.
The scope of the TE18 project is, in summary the construction of a new three storey extension to the existing terminal building, circa 10 000 m2. The works comprise:
— Demolition of existing slabs and structures as required for the works
— All groundworks and provision of new foundations as required by the design
— Installation of new structural frame, cladding and roofing works.
— Installation of Mechanical, electrical and public health systems. Integration of these systems with the Airport’s wider MEP systems where specified.
— Internal fit out of client spaces. (Shop fitting shall be undertaken by the individual retailers and is excluded from the scope of this tender).
— New drainage runs
— The replacement of all life expired check-in related baggage handling system (BHS) mechanical electrical, and control equipment, and associated software platform(s) in support of upgrades to the BHS that are currently being undertaken.
— Early/Compressed Build Baggage store in the North terminal. The works will include the installation new baggage handling system (BHS) mechanical, electrical, and control equipment, and associated software platforms necessary to permit the new additional sortation capacity to operate effectively. This is in support of upgrades to the BHS that are currently being undertaken
In addition, the Construction Manager shall allow for the following requirements:
— Phasing of works as necessary to limit disruption to Airport operations.
— Design of temporary works where required.
— BIM level 2. The Construction Manager will be expected to comply with the requirements of the BIM Execution Plan (see appendix 1).
The following works will be completed by an enabling works contractor and are excluded from the scope of this tender:
— Construction of new build extension re-provide bussing lounge capacity lost to TE18
— Provision of alternative route for Common Travel Passengers
— Refurbishment of existing ‘Champagne Bar’ toilets
— Reconfiguration of existing bussing lounge
— Removal and relocation of existing diesel tank
— New staircase 45
It should be noted that the project is located Airside: All Construction Manager’s staff will be required to undergo security clearance. The security vetting process will be managed by the Construction Manager.
The appointed Construction Manager will be required to enter into an NEC3 contract with the Airport.
As detailed within the procurement documentation
Birmingham Airport reserves the right to cancel the procurement process at its own discretion. The Airport shall not be liable for costs associated with the preparation of expressions of interests and tender bids.
Section III: Legal, economic, financial and technical information
Joint and several liability.
Section IV: Procedure
Section VI: Complementary information
Birmingham
B26 3QJ
United Kingdom
Internet address: www.birminghamairport.co.uk